Crossrail's Final Mile
The closer a promised deadline gets, the more important it is to let bad news into the plan.
Real photographPaddington Elizabeth line station in 2025. This shows the completed facility, not construction or audit conditions in 2018.
Cover images are cropped; detail views retain the full composition. Images are automatically optimized. See the source for the original file.The original plan
The central section was originally scheduled to open in December 2018.
What actually happened
In August 2018, the programme announced it could not meet that date. This case reflects the 2019 audit snapshot.
Where was the difficulty?
The National Audit Office identified an unrealistic schedule, the contractual model and insufficient cost pressure among the factors affecting delivery.
What should the next project carry forward?
Independent scrutiny made the problems public and pushed remaining work toward more realistic assessment.
Update milestones when evidence changes, rather than strengthening commitment to the same dates.
Explore the related conceptEvidence, definitions and limits
NAO, Completing Crossrail, 2019. Early audit figures are not presented as the project's final cost.