Judgment / Tail Risk

The Tail behind the Average

A few very bad outcomes can determine survival. An average cannot tell you whether you can absorb an extreme loss.

All values below are constructed teaching data, not industry statistics or a basis for real commitments.

Risks to examine: Scope changes, data quality, integration complexity and lack of adoption

Each bar is one project · Unit: months12 samples
EXPERIMENT RESULT

P80 · 8.6 months

Approximately 80% of sample durations lie at or below this percentile position (linear interpolation). This is not your project's probability of success.

Small samples, selection bias and changing conditions weaken predictive value. If projects are not comparable, collect better data first.

View project
MAKE IT CONCRETE

What would this look like in everyday life?

The average schedule may be affordable while the slowest project exhausts cash. Examine both scenarios.

A question for you

Could you still cope if things went much worse than usual?